The most critical calculation when setting up an industrial textile facility is capacity sizing. A miscalculated capacity either overloads equipment continuously, halving its service life, or selects an oversized boiler/transformer, burning thousands of dollars in unnecessary energy every month. As of 2026, 6 out of every 10 new workshops in Turkey start with capacity errors — translating to 1+ million TL of unnecessary cost over the long term.
This guide clarifies one calculation: "How many kW of steam generator, kVA of transformer, and electrical infrastructure does my workshop need?" Whether you operate a garment workshop, hotel laundry, dry cleaner, or industrial kitchen, the same formulas apply. Below, six chapters cover why kW calculation matters, the steam-generator kW formula, washing-machine/dryer/press load math, total facility kW load, power-factor compensation, and finally transformer selection — all with practical formulas.
1. Why kW Calculation Matters
Buying equipment without capacity calculation is like cooking from a recipe without measuring. The result either undercooks or burns. Translated to industrial facilities: undersized capacity overloads equipment; oversized capacity is dead-weight investment.
Five main consequences of incorrect sizing:
- Overloading: A boiler/machine running constantly at 95-100% load shortens motor/resistance/burner life by 50-60%. A 10-year piece of equipment fails in 5 years.
- Under-production: An undersized system can't keep up on peak days; guest/customer dissatisfaction follows.
- Wasted capital: An oversized system (e.g. 150 kW where 80 kW would suffice) costs 250,000+ TL more upfront and runs at 30%+ efficiency loss every year.
- Utility surcharges: A poorly-sized large transformer triggers reactive-power penalties from the utility — 15-25% on monthly bills.
- Insurance non-compliance: Insurers don't fully cover facilities without correct capacity reporting; partial payouts on workplace incidents.
The output of correct sizing isn't just a number — it's a reference document. That document is used for utility approval, insurance policy, contractor agreement, and equipment manufacturer warranty. Before any investment decision, get a capacity analysis report signed by an engineer.
We'll work in 4 layers:
| Layer | Formula Output | Used By Which Supplier |
|---|---|---|
| 1. Steam-generator kg/h and kW | Boiler capacity | Boiler manufacturer (Kleppa etc.) |
| 2. Washing + drying kW | White-goods installed power | Washing-machine supplier |
| 3. Press + paskala kW | Ironing-equipment electrical load | Press manufacturer |
| 4. Total facility kW + transformer kVA | Transformer + electrical panel size | Utility + contractor |
This guide shares each layer's formula with worked examples.
2. Steam Generator kW Formula
Steam consumption is one of the most critical line items in any facility. The correct formula sums per-equipment hourly steam consumption with diversity and safety margin applied.
Steam consumption formula:
Total steam (kg/h) = Σ (each equipment's kg/h rating) × diversity (0.7-0.9) × utilization factor (0.8) + 20% safety margin
Then kW conversion: 1 kW thermal ≈ 1.5 kg/h of steam (with efficiency factor).
Typical equipment steam consumption table:
| Equipment | Hourly Steam (kg/h) | Equivalent kW |
|---|---|---|
| Manual ironing press | 8-12 | 5-8 |
| Automatic ironing press | 14-18 | 9-12 |
| Vacuum paskala (wide bed) | 20-28 | 13-18 |
| Vacuum paskala (narrow bed) | 14-20 | 9-13 |
| Manual steam iron | 4-6 | 2.5-4 |
| Form-finisher (jacket form) | 18-24 | 12-16 |
| Industrial ironing table | 6-10 | 4-6 |
| Cylinder iron (small) | 25-32 | 16-21 |
| Cylinder iron (large) | 50-65 | 33-43 |
Worked example — mid-size garment workshop:
| Equipment | Count | kg/h (each) | Total kg/h |
|---|---|---|---|
| Manual press | 4 | 10 | 40 |
| Automatic press | 1 | 16 | 16 |
| Vacuum paskala | 2 | 24 | 48 |
| Steam iron | 2 | 5 | 10 |
| Total (theoretical) | 114 |
Diversity 0.8 → 91 kg/h Utilization factor 0.85 → 77 kg/h Safety margin 20% → 93 kg/h
kW conversion: 93 / 1.5 = 62 kW
Choose one size up from the standard production class: 80 kW central steam generator.
The 20 kW central steam generator suits small workshops (max 30 kg/h output); the 40 kW model suits mid-size facilities (max 60 kg/h); the 80 kW model suits large workshops (max 120 kg/h). For broader product context see /en/industries/konfeksiyon. Once a model is selected, steam distribution efficiency directly affects realised capacity — insulation, condensate return, modulating burner, and other pure-design parameters covered in our Steam Efficiency Optimization guide (25-30% annual energy savings achievable). Equally, verify TS EN 286-1 standard compliance of any boiler purchased — it is mandatory for insurance + tender qualification.
3. Washing Machine and Dryer kW Calculation
Beyond steam, electrical consumption is critical in laundry operations. Industrial washing machines and dryers draw heavy electrical loads; transformer sizing fails without accurate calculation.
Standard industrial washing machine kW values:
| Capacity | Nameplate Power (kW) | Wash Cycle | Hourly Consumption (avg) |
|---|---|---|---|
| 10 kg | 4.5-5.5 | 45-60 min | 3.2 kW |
| 25 kg | 8.5-10 | 50-70 min | 6.5 kW |
| 50 kg | 12-15 | 60-80 min | 10 kW |
| 100 kg | 22-28 | 75-90 min | 18 kW |
| 200 kg | 38-46 | 90-110 min | 32 kW |
Industrial dryer kW values:
| Capacity | Nameplate Power (kW) | Dry Cycle | Hourly Consumption |
|---|---|---|---|
| 10 kg | 5-6 | 35-45 min | 4.5 kW |
| 25 kg | 11-14 | 40-55 min | 10 kW |
| 50 kg | 22-26 | 45-60 min | 18 kW |
| 100 kg | 38-44 | 50-70 min | 30 kW |
Worked example — 100-room hotel laundry (350 kg/day):
| Equipment | Count | Nameplate (each) | Hourly Consumption (avg) |
|---|---|---|---|
| Washing machine (25 kg) | 2 | 9 kW | 6.5 × 2 = 13 kW |
| Dryer (25 kg) | 2 | 12 kW | 10 × 2 = 20 kW |
| Total white-goods | 33 kW |
Diversity 0.7 (washing-drying runs sequentially, not in parallel) → 23 kW
This is a meaningful share of facility electrical load; presses and paskalas use steam for heating, so their electrical load is just motor/vacuum-motor draw.
4. Press + Paskala Electrical kW Load
We sized steam consumption separately, but press and paskala motors also draw electricity. This load is often overlooked but must be included in transformer math.
Press and paskala electrical-load table:
| Equipment | Vacuum/Motor Nameplate (kW) | Hourly Consumption (avg) |
|---|---|---|
| Manual ironing press | 0.5-0.8 | 0.4 kW |
| Automatic ironing press | 1.1-1.4 (pneumatic compressor) | 0.9 kW |
| Vacuum paskala (vacuum motor) | 1.8-2.5 | 2.0 kW |
| Form-finisher | 2.5-3.5 | 2.8 kW |
Continuing the garment-workshop example:
| Equipment | Count | kW (each) | Total kW (nameplate) |
|---|---|---|---|
| Manual press | 4 | 0.7 | 2.8 |
| Automatic press | 1 | 1.3 | 1.3 |
| Vacuum paskala | 2 | 2.2 | 4.4 |
| Press+paskala total | 8.5 kW |
Diversity 0.8 → 6.8 kW
Press and paskala electrical load is smaller than it looks — but don't forget the steam generator's electrical draw: an 80 kW electric boiler adds +80 kW; a natural-gas one adds only ~3 kW for the control panel. Fuel-type choice changes total electrical load 10-100×.
5. Total Facility kW Load and Compensation
Sum all loads, apply diversity + safety margin, and calculate installed power and effective load for the facility.
Continuing the garment-workshop example — total facility kW load:
| Load Item | Nameplate (kW) |
|---|---|
| Steam generator (80 kW gas, control panel) | 3 |
| Washing machines (n/a here) | 0 |
| Press + paskala motors | 8.5 |
| Vacuum motors | 4.4 (above) |
| Lighting + HVAC | 12 |
| Other (compressor, condensate pump) | 8 |
| Total nameplate | 35.9 kW |
Diversity 0.7 → 25 kW Safety margin 20% → 30 kW
Natural-gas steam generator scenario total: 30 kW Electric steam generator scenario total: 30 + 80 = 110 kW
This gap shows that fuel-type choice (natural gas vs electric) radically changes transformer sizing; if natural gas is on-site, electrical infrastructure investment shrinks 200%.
Power-factor compensation calculation:
Industrial facilities are inductive-load dominant (motors, resistance heaters); cosφ naturally runs 0.75-0.85. The utility imposes reactive-power surcharges when cosφ < 0.9 — typically 15-25% on monthly bills.
A compensation panel (capacitor bank) raises cosφ to 0.95-0.98. Cost:
| Facility Size | Compensation Panel Cost | Annual Surcharge Avoided |
|---|---|---|
| 30-50 kW | 45,000-65,000 TL | 18,000-25,000 TL |
| 50-100 kW | 75,000-110,000 TL | 32,000-48,000 TL |
| 100-200 kW | 130,000-180,000 TL | 65,000-95,000 TL |
Payback period typically 2.5-3 years.
6. Transformer Selection and Practical Calculation Table
After calculating the facility's total effective load, the transformer-size selection follows. Understanding the difference between kVA and kW is critical here.
Transformer-sizing formula:
Transformer (kVA) = Effective load (kW) / cosφ × safety margin (1.2-1.3)
Practical transformer-selection table (cosφ 0.95 compensated):
| Facility Effective Load (kW) | Transformer (kVA) Recommendation | Typical Facility |
|---|---|---|
| 20-35 | 30-50 kVA | Small workshop, boutique |
| 35-65 | 50-80 kVA | Mid-size garment workshop |
| 65-110 | 80-160 kVA | Large garment shop, hotel |
| 110-200 | 160-250 kVA | Industrial laundry |
| 200-400 | 250-500 kVA | Resort, commercial garment |
| 400+ | 500-1000 kVA | Mega facility |
Garment-workshop scenario (gas-fired steam):
- Effective load: 30 kW
- cosφ 0.95 (compensated): 30 / 0.95 = 31.6 kVA
- Safety margin 1.25: 31.6 × 1.25 = 40 kVA
- One size up from standard class: 50 kVA transformer
Garment-workshop scenario (electric steam):
- Effective load: 110 kW
- cosφ 0.95: 110 / 0.95 = 116 kVA
- Safety margin 1.25: 116 × 1.25 = 145 kVA
- Standard class: 160 kVA transformer
Transformer types and cost (approximate 2026 prices):
| Transformer Size | Dry-Type Cost | Oil-Filled Cost | Installation Time |
|---|---|---|---|
| 50 kVA | 220,000 TL | 145,000 TL | 2 weeks |
| 100 kVA | 380,000 TL | 245,000 TL | 3 weeks |
| 160 kVA | 540,000 TL | 350,000 TL | 3 weeks |
| 250 kVA | 760,000 TL | 480,000 TL | 4 weeks |
| 500 kVA | 1,250,000 TL | 780,000 TL | 5 weeks |
Practical capacity-calculation checklist:
- List all equipment's steam consumption (kg/h)
- Apply diversity + safety margin → calculated steam load
- Convert to kW (kg/h ÷ 1.5)
- Select one size up from standard production class (e.g. 62 kW calc → 80 kW)
- Sum washing machine + dryer electrical loads
- Sum press + paskala motor loads
- Sum lighting + HVAC + other loads
- Total nameplate × diversity + safety margin = effective load
- Divide by cosφ → kVA, add 25% safety margin
- Select transformer from standard sizes
For more complex facilities (e.g. 500 kg/day hotel laundry + industrial kitchen integration), an engineer-signed capacity analysis report from the Kleppa team is recommended. With 12+ years of field experience, our team prepares facility-specific calculations — contact us via /en/get-quote or message our technical team via WhatsApp at +90 533 048 4321. Our first capacity analysis report is free.
If you are sizing a hotel laundry, read this guide alongside the Laundry Operational Cost Optimization guide — even a correctly sized boiler still leaks 1.2-1.7M TL/year of hidden cost without operational optimization.
For authoritative technical reference, consult the Turkish Standards Institute's TS EN 12953 steam-boiler standard and the Turkish Chamber of Electrical Engineers' industrial transformer-sizing guideline; both define the conformity framework that Kleppa boilers and system designs are built within.




